Submitted by InfraRisk on Thu, 03/05/2015 - 17:15


The eighteenth month progress meeting took place over two days, on the 5th and 6th of March 2015. The meeting, hosted by CSIC, took place in the historical Residencia de Estudiantes del CSIC in Madrid, Spain and was attended by representatives from all eleven consortium partners. The meeting was timed to occur with the end of Period 1 of the project (Month 1 to Month 18). The purpose of the meeting was to assess the project progress and discuss the various administrative and technical issues. On the first and second days of the meeting WP leaders presented an update on their progress, which was followed by open discussions among all partners on the material presented. A Steering committee meeting took place at the end of the second day with issues related to Coordination activitities being the primary focus for discussion.